Four things decide whether an LNG or gas infrastructure asset earns what it is supposed to. Here they are, and here is where these projects actually come apart.
In this sector the plant is rarely what you are buying. You are buying a contract, and the plant is the thing that has to keep performing for the contract to pay.
So the offtake gets read first, and read properly. Is the volume firm or is it reasonable-endeavours dressed up. Is it take-or-pay, and if so what relieves the buyer. Is pricing indexed to oil, to a gas hub, or to a formula that stops making sense in a different price environment. Is there destination flexibility, and who captures the value when cargoes get diverted.
Then the two questions people skip. Who actually stands behind the obligation — an operating subsidiary with no balance sheet is not the same counterparty as its parent. And does the tenor of the contract match the tenor of the debt above it. A fifteen-year facility sitting over a seven-year offtake is a refinancing risk that has been renamed.
Liquefaction projects are marketed on demand. They fail on supply.
Reserves are not deliverability. What matters is whether committed molecules arrive at the inlet at the pressure and composition the plant was designed for, on the day, for twenty years — which depends on reservoir performance, compression, the gathering system, and whoever else has a claim on the same gas, including a domestic market obligation that can be reimposed by a government under pressure.
The same discipline applies in reverse at a regasification terminal, where the question is whether the downstream offtaker can physically take the send-out: pipeline capacity, grid acceptance, and the seasonality of demand against the cost of holding inventory.
If the upstream story is thin, nothing downstream saves it. We have seen more value destroyed by feedgas assumptions than by price.
These projects fail upstream of the plant far more often than they fail in the market.
The liquefaction train, the tanks and the process units get the scrutiny because they are the big line items. The overruns tend to arrive somewhere else.
Marine works and dredging. The jetty and its availability once weather downtime is honest rather than optimistic. Berth rights and who else has them. Storage volume against cargo size and shipping schedule, which sets how much flexibility exists before production has to be curtailed. The pipeline interconnection and whoever controls the tariff on it. Power and utilities, and whether the site is islanded or exposed to a grid that is not reliable.
None of it is exotic. All of it is where a schedule slips and a budget goes, and it is the part of a data room that has usually had the least attention.
The failure modes repeat, and they are worth stating plainly.
Upstream underdelivers. The gas is there and will not flow at the rate the plant needs. The EPC contract leaks. Scope sits outside the wrap, the contractor is thin, and the liquidated damages do not begin to cover a delay. The regulator moves. A tariff is reset, a domestic obligation is imposed, an export licence is reinterpreted. The counterparty degrades. Credit that looked adequate at signing is not adequate five years in, and there is no step-in worth the paper. The operator cannot operate. Utilisation settles ten points below nameplate and never recovers.
Every one of those is visible in advance to someone who knows what to ask. That is the work we do before capital moves, and it is the reason we can commit quickly when the answers hold up.